NEW QUESTION 46
Which is a minimum requirement when applying the business case theme?
- A. To specify the solution to be used to deliver the business option selected
- B. To ensure the corporate business plan is updated with the project costs and benefits
- C. To integrate the benefits management approach with the project and stage plans
- D. To define the management actions required to ensure the project's outcomes are achieved
Answer: A
NEW QUESTION 47
Which is a purpose of an Exception Plan?
- A. Define the changes which are within the scope of the change budget
- B. Reduce the number of exception assessments, by agreeing a budget to cover the costs of any requests for change
- C. Identify the actions required to recover from the effect of a tolerance deviation
- D. Show the reason for the tolerance deviation from a Stage Plan or Project Plan
Answer: C
NEW QUESTION 48
What must be produced to meet the minimum requirements for applying the change theme?
- A. Details of the status of all products being produced
- B. Documentation on the version of each product
- C. Documentation on the corrective action for an issue
- D. Details of the decisions taken on all issues
Answer: D
Explanation:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Themes#Change_Theme
NEW QUESTION 49
How should the Team Manager report that tolerances are forecast to be exceeded?
- A. Create a Highlight Report
- B. Raise an issue
- C. Create an Exception Report
- D. Grant a concession
Answer: B
NEW QUESTION 50
When should the Project Board refer to corporate or programme management for a decision?
- A. The Senior Supplier or Senior User needs to be changed
- B. It is forecast that project level tolerance will be exceeded
- C. Any request for change needs to be approved
- D. The stage requires resources
Answer: B
NEW QUESTION 51
Which theme defines the accountability for realization of the project's benefits?
- A. Plans
- B. Organization
- C. Progress
- D. Quality
Answer: B
NEW QUESTION 52
If a project's benefit tolerance is forecast to be exceeded, to whom should this be escalated to for a decision?
- A. Corporate/programme management
- B. Senior User
- C. Senior Supplier
- D. Executive
Answer: A
NEW QUESTION 53
Which statement about applying the 'tailor to suit the project' principle is CORRECT?
- A. A technically complex project should NOT tailor PRINCE2
- B. PRINCE2 can be tailored to be used with any type of project
- C. The tailoring of PRINCE2 is MOST appropriate for agile projects
- D. A project which is part of a programme should NOT tailor PRINCE2
Answer: B
Explanation:
Reference: http://prince2.wiki/Tailoring
NEW QUESTION 54
Which is a purpose of the Managing a Stage Boundary process?
- A. Review and close any risks and issues identified during the previous stage
- B. Control the link between the Project Manager and the Team Manager(s)
- C. Provide the Project Board with sufficient information for approving the next stage
- D. Approve the next Stage Plan
Answer: C
Explanation:
Section: Volume B
NEW QUESTION 55
How many management stages should a PRINCE2 project consist of?
- A. Initiation stage and at least one other management stage to cover the remainder of the project
- B. Start up stage, initiation stage and a closing stage
- C. Start up stage, at least one other management stage to cover the remainder of the project and a closing stage
- D. Start up stage, initiation stage and at least one other management stage to cover the remainder of the project
Answer: A
Explanation:
Section: Volume B
NEW QUESTION 56
Which is a purpose of an End Stage Report?
- A. Provide a plan for the next stage of the project
- B. Summarize progress to enable the Project Board to decide what action to take next
- C. Summarize how the project performed against the version of the Project Initiation
Documentation used to authorize it - D. Provide the detailed analysis of a deviation and offer options for the way to proceed
Answer: B
NEW QUESTION 57
Which regular report provides the Project Board with a summary of stage status?
- A. Checkpoint Report
- B. Communication Management Strategy
- C. Project Brief
- D. Highlight Report
Answer: D
NEW QUESTION 58
Which is a typical core activity within configuration management?
- A. Risk management
- B. Verification and audit
- C. Quality assurance
- D. Progress reporting
Answer: B
NEW QUESTION 59
What is defined as a temporary organization that is created for the purpose of delivering one or more business products?
- A. Corporate or programme management
- B. A product breakdown structure
- C. A project
- D. A user group
Answer: C
NEW QUESTION 60
Identify the missing word(s) in the following sentence. During a quality review meeting [ ? ] any identified defects.
- A. the chair will approve the solution to
- B. an issue should be created for
- C. a solution should be designed for
- D. the agreed actions should be recorded for
Answer: D
NEW QUESTION 61
Which is NOT considered when defining risk tolerance?
- A. A Project Board's attitude towards risk taking
- B. An organization's risk appetite
- C. The allocated risk budget
- D. The amount of risk a Project Board considers acceptable
Answer: C
NEW QUESTION 62
Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?
- A. Only corporate or programme management
- B. Only the Project Manager
- C. All levels of management
- D. Only the Project Board
Answer: C
NEW QUESTION 63
......