NEW QUESTION 22
Which is an objective of the quality review technique?

  • A. To define the quality methods required within a project
  • B. To baseline a product
  • C. To determine the quality responsibilities of a project team
  • D. To provide a common understanding of what products a project will create

Answer: B

 

NEW QUESTION 23
Which is a purpose of the 'initiating a project' process?

  • A. To identify the number of work packages required
  • B. To establish solid foundations for a project
  • C. To decide if it is worthwhile to initiate a project
  • D. To decide on the project approach

Answer: B

Explanation:
Explanation
Reference http://prince2.wiki/Initiating_a_Project#Objective

 

NEW QUESTION 24
Which is one of the three levels of plan in PRINCE2?

  • A. Project Brief
  • B. Programme Plan
  • C. Benefits Review Plan
  • D. Team Plan
  • E. Explanation:
    QUESTIONNO:160
    Which of the following statements about quality assurance and Project Assurance is true?
    A. Project Assurance is the responsibility of the corporate organization; quality assurance is the responsibility of the Project Board
    B. Project Assurance is independent of the Project; quality assurance is only independent of the Project Manager
    C. Project Assurance may be delegated within a project; quality assurance must be undertaken by the Project Board
    D. Project Assurance ensures compliance to standards within the project environment; quality assurance ensures compliance across the organization

Answer: D

 

NEW QUESTION 25
Which statement about the Directing a Project process is FALSE?

  • A. Is triggered by a request to initiate a project
  • B. Covers the day-to-day activities of the Project Manager
  • C. Provides a mechanism for the Project Board to assure that there is continued business justification
  • D. Supports the PRINCE2 principle of manage by exception

Answer: B

 

NEW QUESTION 26
Which two roles are linked by the Managing Product Delivery process?

  • A. Project Manager and TeamManager
  • B. Corporate or programme management and Project Board
  • C. Team Manager and external supplier
  • D. Project Board and Project Manager

Answer: A

 

NEW QUESTION 27
Which is a purpose of the Controlling a Stage process?

  • A. Produce a Team Plan for the work to be assigned to a Team Manager
  • B. Select and implement actions that will resolve deviations from a plan within tolerance
  • C. Obtain approvals for products delivered in a Work Package
  • D. Update a Project Plan to incorporate the actuals from a Stage Plan

Answer: B

 

NEW QUESTION 28
What must be produced to meet the minimum requirements when applying the change theme?

  • A. Records of the decisions made on all issues
  • B. Documents recording the version of each product
  • C. A change budget for the analysis of change
  • D. Status reports on all products being produced

Answer: A

Explanation:
Section: Volume B

 

NEW QUESTION 29
Which statement about the Directing a Project process is true?

  • A. Ensures there are regular progress meetings
  • B. Covers the day-to-day activities of the Project Manager
  • C. Provides a mechanism for the Project Board to assure that there is continued business justification
  • D. Begins on completion of the Initiating a Project process

Answer: C

Explanation:
Section: Volume A

 

NEW QUESTION 30
Which is NOT a purpose of a Benefits Review Plan?

  • A. Define the scope, timing and ownership of the benefit reviews required
  • B. Describe how to measure and confirm anybenefits that are to be realised after the project is closed
  • C. Describe how to measure the performance of the project's products in operational use
  • D. Define the periodover which the cost-benefit analysis will be based

Answer: D

 

NEW QUESTION 31
Which is a type of issue?

  • A. An Exception Report
  • B. A lesson
  • C. A request for change
  • D. A risk with an estimated high impact

Answer: C

Explanation:
Section: Volume A

 

NEW QUESTION 32
Which PRINCE2 principle is being applied when tolerances are set to establish limits of authority and accountability?

  • A. Defined roles and responsibilities
  • B. Manage by exception
  • C. Manage by stages
  • D. Continued business justification

Answer: B

Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Manage_by_exception

 

NEW QUESTION 33
Which is NOT a PRINCE2 principle?

  • A. Defined roles and responsibilities
  • B. Customer/supplier environment
  • C. Learn from experience
  • D. Continued business justification

Answer: B

 

NEW QUESTION 34
Which is an objective of the Managing a Stage Boundary process?

  • A. Review and approve the next Stage Plan
  • B. Assure the Project Board that all project products have been completed and approved
  • C. Prepare an Exception Report to advise the Project Board of aforecast deviation from tolerance
  • D. Understand what has gone well and what can help the next stage

Answer: D

 

NEW QUESTION 35
Which are benefits of using PRINCE2?
1. It removes the need for activity-based planning
2. It promotes learning and continuous improvement
3. It can be applied to any type of project
4. It defines specific leadership and other interpersonal skills required

  • A. 1 and 4
  • B. 2 and 3
  • C. 1 and 2
  • D. 3 and 4

Answer: B

Explanation:
Section: Volume B
Explanation/Reference: https://www.axelos.com/best-practice-solutions/prince2/key-benefits-of-prince2

 

NEW QUESTION 36
Which aspect of project performance must be managed to avoid misunderstandings on what the project is to deliver?

  • A. Risk
  • B. Costs
  • C. Timescale
  • D. Scope

Answer: D

 

NEW QUESTION 37
Which is an objective of the Closing a Project process?

  • A. Prepare the plan for the next stage
  • B. Assess any benefits that have already been realized
  • C. Produce a Benefits Review Plan to identify what benefits are expected
  • D. Check that all benefits are realized before closing a project

Answer: B

 

NEW QUESTION 38
Which is a purpose of a lessons log?

  • A. To escalate lessons to the project board
  • B. To raise improvements with project assurance
  • C. To record any lessons that are raised in checkpoint reports
  • D. To document that corrective action is being taken

Answer: C

Explanation:
Explanation/Reference:
Reference https://mplaza.pm/prince2-lessons-log-template/

 

NEW QUESTION 39
Which is a purpose of the 'directing a project' process?

  • A. To delegate day-to-day management of the project to the project manager
  • B. To control the day-to-day running of the project
  • C. To create and authorize the project mandate
  • D. To ensure that work on products allocated to the team is authorized and agreed

Answer: A

Explanation:
Section: Volume B
Explanation/Reference: https://www.prince2primer.com/directing-a-project-in-prince2/

 

NEW QUESTION 40
Which of the following take place before the initiation of a project?
1 . Appoint the Executive
2 . Capture requirements
3 . Develop the Project Brief
4 . Develop the detailed Business Case

  • A. 1, 3, 4
  • B. 2, 3, 4
  • C. 1, 2, 3
  • D. 1, 2, 4

Answer: C

 

NEW QUESTION 41
Which plan provides the Business Case with costs during the Initiating a Project process?

  • A. Team Plan
  • B. Stage Plan
  • C. Project Plan
  • D. Initiation Stage Plan

Answer: C

 

NEW QUESTION 42
Which theme estimates the cost of delivering the project?

  • A. Business Case
  • B. Progress
  • C. Plans
  • D. Change

Answer: C

Explanation:
Section: Volume B

 

NEW QUESTION 43
Which is an objective of the Closing a Project process?

  • A. Prepare the plan for the next stage
  • B. Assess any benefits that have already been realized
  • C. Produce a Benefits Review Plan to identify what benefits are expected
  • D. Check that all benefits are realized before closing a project

Answer: B

Explanation:
Section: Volume A

 

NEW QUESTION 44
Which of the following is NOT part of quality planning?

  • A. Define quality responsibilities
  • B. Gain acceptance of the project product
  • C. Agree acceptance criteria
  • D. Set quality tolerances

Answer: B

 

NEW QUESTION 45
Where can people who join a project after initiation quickly and easily find information about how the project is being managed?

  • A. Project product description
  • B. Project brief
  • C. Project initiation documentation
  • D. Project mandate

Answer: C

 

NEW QUESTION 46
Which are purposes of the quality theme?
1. To implement continuous improvement during the project
2. To establish how the project will ensure that products created will be acceptable to key stakeholders
3. To ensure that the project is desirable and achievable
4. To identify, assess and control uncertainty

  • A. 1 and 4
  • B. 2 and 3
  • C. 1 and 2
  • D. 3 and 4

Answer: B

Explanation:
Explanation
Reference https://www.whatisprince2.net/prince2-theme-quality.php

 