NEW QUESTION 11
Refer to the exhibit.
The network architect has created the 60M shown in the exhibit tor a complete new wired ana wireless solution for a customer. This solution the customer wants to discover and manage every component or the network in Airwave, including twins, MCS, APS, and switches.
How many AirWave licenses dees the architect need to add?
- A. 0
- B. 1
- C. 2
- D. 3
Answer: C
NEW QUESTION 12
What is one customer requirement that can drive the need for a relatively dense AP deployment. In which ire coverage areas of at least three AP radios overlap?
- A. AP operation as hybrid AMs for IDS/WIPS
- B. location tracking of wireless loT devices
- C. support for beacon management
- D. the deployment of dual SGHz radio APs
Answer: C
NEW QUESTION 13
What is one additional benefit trial Foundation Care gives beyond ire included warranty in Aruba products?
- A. Next Business Day Snipping
- B. installation and getting started services
- C. business hour prone support for hardware issues
- D. unlimited 24x7 access to TAG and online support
Answer: A
NEW QUESTION 14
Refer to the exhibit.
The exhibit shows the topology for a new Aruba solution. The MCs are in a ctuster and support all of the wireless traffic in the network The core switches route all traffic and support all VLANS. The access fayer switches do NOT use tunneiednode. or dynamic segmentation.
The customer has indicated that it has these VLANS for user devices.
* VLAN 11 for Floori employee wired devices
* VLAN 12 for Floor 2 employee wired devices
* VLAN 13 tor Floor 3 employee wired devices
* VLAN 14 for Floor 4 employee wired devices
* VLAN 15 for Floor 5 employee wired devices
* VLAN 101 for all employee wireless devices
* VLAN 102 for all guest wireless devices
In which locations should the architect plan the VLANs?
- A. VLANs 11-15 on the access layer switches on the corresponding floor; VLAN 101 on one MC and VLAN 102 on me other MC
- B. VLANs 11-15 on one MC. VLANs 101 and 102 on the other MC. (Other VLANs will be used on the access layer switches.)
- C. VLANs 11-15. 101. and 102 on both MCs. (Other VLANs will be used on the access layer switches.)
- D. VLANS 11-15 on the access layer switches on the corresponding floor; VLANS 101 and 102 on both MCS.
Answer: A
NEW QUESTION 15
An indoor basKetbaiI stadium has 5.000 seats in two rings:
* The stadium has a ceiling height of GO feet (18 m).
* There is a catwalk around the perimeter of the basketball court, between the court and the seating areas.
* This catwalk is 40 feet (12 m) from the floor.
* There are two scoreboards at either end of the stadium.
* The construction of the stadium is concrete and sleet.
The customer does not want an under-seat, picoceli deployment.
Which AP model is appropriate to provide coverage in the main stadium bawl?
- A. AP-577
- B. AP-555
- C. AP-505
- D. AP-575
Answer: A
NEW QUESTION 16
Refer to the exhibit.
This warehouse has the dimensions shown in the exhibit. The warehouse is 20 feet (6 m) high up to a steel railing on the celling. The shelves are about 16 feet (5m) high, and they hold large containers filled with fluid and metal equipment.
The customer needs consistent wireless coverage throughout the warehouse, mostly to support the tablets that employees use to run Inventory tracking and other applications. The warehouse staff works in shifts of 20.
The architect has selected AP-515S. About how many APs should the architect propose?
- A. about 6-4
- B. about 13-16
- C. about 6-8
- D. about 23-32
Answer: C
NEW QUESTION 17
What is one piece of additional information architects should obtain from the customer before they design the wireless solution?
- A. the distance between the locations where cameras will be installed and the wiring closet on each floor
- B. the power requirements for the wireless loT devices and security cameras
- C. the average number of users per loT device
- D. the authentication and encryption capabilities for loT devices and security cameras
Answer: A
NEW QUESTION 18
A retailer wants to add a wireless network to its stores to provide guest access. The store has wired POS systems which the customer will now replace with wireless systems.
The APs will he installed on the ceilings, which are about S feel (2.4 m) high.
What is one feature on the APs that can help the customer comply with PCI DSS?
- A. Anomaly-based threat detection
- B. Smart Rate ports
- C. Physical security with Kensington Security Slots
- D. User and Entity Behavior Analytics (UEBA)
Answer: B
NEW QUESTION 19
Refer to the exhibit.
A hotel needs a wireless solution, i he hotel has 802.3af switches.
The architect has selected the 505H Series, controlled by a local MC as the best choice The 5QoH series will need to power a connected phor which have only a single Ethernet port. The architect has created the BOM shown in the exhibit. (Note that this portion of the BOM does not inc Which correction should the architect make?
- A. Upgrade to PoE+ switches.
- B. Change the 5Q5H to the 3Q3HR model.
- C. Remove the mounting adapters.
- D. Propose new direct power source for phone.
Answer: D
NEW QUESTION 20
A customer requires new MCs for a large multi-site network with about 600 AP-535S ana 30,000 wireless clients. The customer requires redundancy for the MCs, with each MC being able to handle the full toad in a failover situation The network should be able to sustain the loss of a controller with stateful failover within seconds. It should be able to undergo software upgrades without downtime.
The architect has recommended two 7240XM MCs. The customer points out that 7220 MCs can support their requirements and wonders why the architect recommended me 7240XMS.
What should the architect explain?
- A. The 7240XM MCs have better redundant power supplies and fan tray component capabilities than 7220 MCs.
- B. The 7240XM MCS provide a higher number of concurrent GRE tunnels to support 600APs with MCS in L2 clustering.
- C. The 7240XM MCs are required to support the large number of wireless clients in this network
- D. The 724QXM MCs can support full CPSec tunnels with this number of APs. while the 7220 MCs cannot.
Answer: C
NEW QUESTION 21
Refer to the exhibit.
A stadium wants to deploy location-based services, including blue-dot wayfinding over a 200.000 square root (isr580 sq. m) are a. The custom past particular areas. The customer has selected a 1 year subscription.
The exhibit shows the BOM that the architect created in iris.
Which correction should the architect make?
- A. Add another campaign subscription.
- B. Add two Maps subscriptions.
- C. Remove one Blue Dot Nav subscription.
- D. Change the campaign subscription to a Maps subscription.
Answer: D
NEW QUESTION 22
Compare the scenarios below. For which scenario do AP-575S meet the needs?
- A. The customer needs APs for an indoor stadium that requires overhead coverage and directional antennas.
- B. The customer needs to mount APs in an outdoor area, but that area only has fiber cable available,
- C. The customer needs APs for an Indoor nigh density environment In which tne customer prefers dual 5GHz operation.
- D. The customer needs APS mounted to a concrete building exterior to provide coverage in a 90 foot (27m) radius from the building.
Answer: B
NEW QUESTION 23
A hospital needs a Getter way to track its inventory Including wireless medical devices that are moved around the site a lot.
Which solution meets these needs?
- A. Aruba asset tags and beacons
- B. Aruba beacons. APs. and AirWave
- C. Aruba beacons and Meridian
- D. Aruba asset tags, APs; and Meridian
Answer: C
NEW QUESTION 24
Refer to the exhibit.
A customer has the wined infrastructure shown in the exhibit. The customer is in the process of expanding their wireless services They will now add a new wireless solution, with mobility controllers (MCs) connected as shown. The new wireless solution will support a total of 450 APs and about 26,000 wireless devices. It must provide seamless roaming across the entire campus.
After the new deployment, both wired and wireless devices experience IP connectivity issues.
Which change to the existing infrastructure should the architect recommend to support all of the customer requirements?
- A. The wired VLANS should be combined into a single VLAN and n6 subnet
- B. The MCs should be moved to the aggregation layer, and more MCs added
- C. The core and aggregation switches should disable Virtual Switching Framework (VSF).
- D. The core switches should be replaced with switches that have larger ARP tables.
Answer: C
NEW QUESTION 25
Refer to the exhibit.
The exhibit shows the current AP deployment in a school. This customer indicates that the current wireless performance is inadequate and w B02.11ax.
For the new' solution, what should the network architect recommend?
- A. APs deployed in similar locations, but with dual 5 GHz radios
- B. APs deployed in hallways with about twice the density
- C. APS deployed in similar locations, but with higher gain antennas
- D. APs deployed in rooms with a density-based design
Answer: B
NEW QUESTION 26
Refer to the exhibit.
A customer needs to create a proposal for a full wireless solution for a customer The customer has indicated that the MCs will connect to Aru&a CX Switches at the core and the APs will connect to PoE-i- switches at the edge. The customer requires that the wireless solution support at least 50 Mbps concurrently per AP. The architect has created a BOM tor a Mobility Master (MM), two MC 721os, and 400 AP-535S. me exhibit snows this BOM.
Which components has the architect forgotten?
- A. Mounting Kits tor the MOs and MM
- B. Smart Rate PoE+ injectors for the APs
- C. Sufficient Enterprise licenses for the APs on both MCs
- D. SFP+ transceivers tor the MC connections
Answer: A
NEW QUESTION 27
A customer has an Aruba wireless network. which includes two MC 7205s and an MM at the network core. The company now wants to accommodate 50 mobile trainers These trainers travel around the world and run training events. The trainers often need to access materials in the company data center, but cannot reach materials when they are on the road.
The company wants to give the mobile workforce a secure way to reach the materials they need no matter where they are.
including in public spaces like the hotels where they often leach. The customer also requires that the solution be as cost effective as possible while meeting the requirements.
Which plan meets the needs of the mobile Trainers?
- A. Add 50 RAPs: add 50 Enterprise licenses to the MM, and add two 7005 MCs in the DMZ.
- B. Add so PEFV licenses to the MM. and add an additional 7205 MC to the core.
- C. Add 50 RAPs; add 50 Enterprise licenses and 50 VIA licenses to the MM
- D. Add 50 VIA licenses to the MM, and deploy two 7005 MCs in the DMZ.
Answer: C
NEW QUESTION 28
For which scenario do Aruba CX 6300M Series switches meet the needs for an upgrade of the wired access layer while the Aruba CX 630QF Series switches do not?
- A. The customer wants to utilize the Aruba AP-515 support for 002 3bz connectivity.
- B. The Aruba CX6300M supports 10GBase-T connectivity with AP-515.
- C. The customer wants to utilize LACP on AP515 in VSF switch configuration.
- D. The Aruba CX 630DM support up to 75W PoE+ per port
Answer: D
NEW QUESTION 29
A retailer currently has two redundant ClearPass C2000 0L36O Gen9 hardware appliances and two perpetual 1K Access licenses. The customer uses ClearPass to authenticate employee wireless devices and other corporate wireless devices. ClearPass togs indicate that, peak license usage is currently 1900.
The customer now wants to add a guest access solution. Guests will connect to an open SSiD and be redirected to a portal which they can use to self-register and log in. The customer anticipates that up to f 550 guest devices will connect at the same time.
The customer requires the most cost-effective solution that will meet the requirements. What should the network architect recommend for this solution?
- A. 1K + 500 Access licenses; Two 1K Onboard licenses
- B. Two 1K Guest licenses
- C. IK + 500 Access licenses: IK + 500 Guest licenses
- D. 1K + 500 Access licenses
Answer: B
NEW QUESTION 30
A nospltai needs an upgrade to 802.11ax for its wireless network, which needs to provide complete coverage The hospital has a concrete exterior and uses drywalls lor all of the interior walls with a few exceptions as mandated for safety The building has 10fool (3 m) ceilings.
The hospital prefers to avoid the deployment of APs in rooms if possible. Exceptions include reception areas and lounges.
The wireless network must support wireless medical devices, voice communicators for medical star, laptops in nurse stations, medical staff tablets, and visitor and patient personal devices. All of these devices support both the 2.4GHz and 5GHz band.
The exhibits below show one wing of one floor of the hospital. This wing is about 2S.Q0D square feet {2GQQ sq, m). The unlabeled rooms along the bottom of the wing are patient rooms' other rooms such as lounges and the MR] room are labeled. This area has:
* up to SO concurrent patients and visitors, who might have up to two devices
* 40 concurrent staff members, who might have up to three devices
* about 200 medical and other types of wireless devices
The architect has already planned to place APs in stairwells on another floor.
Which AP plan for this wing of this floor meets the customer needs?
A)
B)
C)
D)
- A. Option A
- B. Option D
- C. Option B
- D. Option C
Answer: A
NEW QUESTION 31
Which scenario Indicates the need for a wireless mesh?
- A. A company needs to provide seamless roaming and wireless access between two buildings. The buildings are about 60 feet (18 m) apart.
- B. A company has a small branch office with just one RAP. The company has noticed that performance is poor in some areas of the network and wants to add another AP.
- C. A hospital needs to provide high availability for wireless services in certain areas which support very critical wireless medical devices. Devices must always be in range of at least two APs.
- D. A nsstorical building has some wired areas and a few areas with no wired or wireless connectivity, walls and ceilings have asbestos. The company needs wireless access across the site.
Answer: A
NEW QUESTION 32
Refer to the exhibit.

A customer needs a new branch office solution that:
provides 802.11ac wireless access to local resources and the local Internet connection connects wired and wireless users to resources at the main office in a secure manner The office has 200 users, who will the up to two wireless devices at the same time. The architect has determined that the office requires 10-13 AP-
515s. The customer wants to support a total bandwidth from an or me APS or about 2 cops.
The entire site is currently wired for CAT5e from a single wiring closet, which contains two access switches, a core switch, and the Internet cable modem, which has 10/10O/1OQO Mbps BASE-T ports. The wired networK will handle abouti Gbps of traffic. The switches do not support P0E/P0E+.
About 75 percent of all traffic is destined to the main office
The architect has looked up these specs for 7000 series controllers.
Which MC will meet the needs in the most cost-effective manner?
- A. 0
- B. 1
- C. 2
- D. 3
Answer: C
NEW QUESTION 33
......